University Street Paving Completed Ahead of Schedule
The municipality announced completion of University Street paving two weeks ahead of schedule.
Public Relations Department
Beit Ur Al-Tahta Municipality
The municipality announced today that University Street paving was completed two weeks ahead of schedule, and 8% under the allocated budget.
Project Figures
- Street length: 2.4 kilometers
- Actual budget: ILS 230,000
- Actual duration: 56 days
This achievement reflects efficient planning and a strong commitment to service delivery.
The next phase will include installation of new LED street lighting along the corridor.